Xinyue Flange Welded Pipeline Supports Saudi Dredging Project.

Project location:Saudi Arabia

Product:Flange Welded Pipes

Standard and material:

ASTM A53 GR B

Specifications:

690mm*20mm*12000mm

740mm*20mm*12000mm

Application:Dredging Project

Inquiry time:2022.04.20

Order time:2022.05.24

Shipping time:2022.08.20

Arrival time:2022.10.10

This time, we will continue to talk about the dredging project of Saudi contractor. Following the successful shipment of welded

split elbow and refined flange in July, the second batch of ordered products, flange welded pipe, was successfully shipped again in August.

According to the project requirements, flanges shall be welded at both ends of steel pipes. In order to ensure

that the flanges are complete and not easy to be damaged during transportation, in the early project regular meeting,

after many studies and discussions, it was finally decided to adopt the method of wood frame and angle steel fixation,

then wrap the flanges at both ends of the steel pipes into the wood frame, so as to effectively protect the flanges

and make the whole batch of steel pipes be delivered to customers in good condition. At present,

the product has been put into use with good customer feedback.